Hutchinson Builders are making good progress on site with ground works advancing without any major hurdles. Works completed to date include all early works and piling and the major part of the bulk earth works. The retention system for the rear property alignment has been completed allowing the basement structures, including ramps, loading bays and sub stations, to advance and be well underway.

Works will continue in the coming weeks and will see the construction team working on several fronts, including the completion of bulk earth works, lift pits and the basement floor slabs being formed and poured. The tower crane installation and the services for the basement level are all scheduled to commence.