Construction Progress Stage 4:

  • Slabs now completed
  • Timber Framing 85% complete
  • Roof installed on 8 units
  • Roughly 40% complete
  • Windows delivered and loaded out to site.
  • Roof commencing on block K this Friday
  • Hebal to commence next week
  • Roof trusses on Units 2 & 3 to commence this week
  • NBN application now lodged

STAGE 4 REFERENCE: Lots 2 – 15
Completion: RCQ Builders are on programme for a completion in Late June with settlement expected in July.